Enauta informed they´ve resumed planning the return to production in Atlanta field, in the post-salt Santos Basin, in October. The initial expectation was to restart the process in September. however, the company stopped production in July after failures in the electrical components of the submarine pumping equipment, discovered during a scheduled stop for maintenance of the FPSO Petrojarl I. In August, commissioning and testing of new components were made. The first oil from the new platform is scheduled for mid-2024. This month, Enauta expects to complete the last producing well of the set of six wells set planned for Phase I in Atlanta and will start mooring the FPSO Atlanta.