Two important milestones have just been reached on the Atlanta project (Enauta) this month: the flexible risers have embarked on BBC Chartering BBC Greenland with ETA Rio de Janeiro 30th March 2024. These are the last components of the subsea system of the field to depart to field. Conversely the FPSO Atlanta has started her journey to Brazil today and is expected to arrive in early May. After being hooked up and lines pulled in, first oil is expected within August.