Offshore Highlights


• Karoon Energy has resumed production at the Baúna Field in the Santos Basin after a 20-day planned maintenance. With the SPS-88 well back online, output increased to approximately 26,500 bopd, exceeding pre-shutdown levels.

• The hull of FPSO P-80 has departed the CIMC Raffles shipyard in China and is now en route to Singapore, where Seatrium will handle the topside module integration. The unit is expected to begin operations in the Búzios Field, pre-salt Santos Basin, in 2027.

• BW Offshore has reached a settlement with PRIO over the long-standing dispute involving the FPSO Polvo, ongoing since 2021. The Norwegian Owner is due to receive around USD 36 million.